Map Location Key Station Type Capacity (Net) (MWe) Operator Status Reactor Supplier Construction Begun Criticality Date Grid Connection Date Commercial Date Decomission Date
1 OMA ABWR 1383(Gross) Electric Power Development Planned Mar-05 Jul-10 2 TOMARI-1 PWR 550 HEPCO Operating MHI 02-Jul-85 16-Nov-88 06-Dec-88 22-Jun-89 2
TOMARI-3
PWR
866
HEPCO
Planned
2003
2009
2 TOMARI-2 PWR 550 HEPCO Operating MHI 05-Aug-86 25-Jul-90 27-Aug-90 12-Apr-91 3 ONAGAWA-1 BWR 498 TOHOKU Operating TOSHIBA 08-Jul-80 18-Oct-83 18-Nov-83 01-Jun-84 3 ONAGAWA-2 BWR 796 TOHOKU Operating TOSHIBA 12-Apr-91 02-Nov-94 23-Dec-94 28-Jul-95 3 ONAGAWA 3 BWR 796 TOHOKU Operating TOSHIBA 23-Jan-98 26-Apr-01 30-May-01 30-Jan-02 4 FUKUSHIMA-DAIICHI-1 4 BWR 439 TEPCO Operating GE 25-Jun-67 10-Oct-70 17-Nov-70 26-Mar-71 4 FUKUSHIMA-DAIICHI-2 BWR 760 TEPCO Operating GE/TOSHIBA 09-Jun-69 10-May-73 24-Dec-73 18-Jul-74 4 FUKUSHIMA-DAIICHI-3 BWR 760 TEPCO Operating TOSHIBA 28-Dec-70 06-Sep-74 26-Oct-74 27-Mar-76 4 FUKUSHIMA-DAIICHI-4 BWR 760 TEPCO Operating HITACHI 12-Feb-73 28-Jan-78 24-Feb-78 12-Oct-78 4 FUKUSHIMA-DAIICHI-5 BWR 760 TEPCO Operating TOSHIBA 22-May-72 26-Aug-77 22-Sep-77 18-Apr-78 4 FUKUSHIMA-DAIICHI-6 BWR 1067 TEPCO Operating GE/TOSHIBA 26-Oct-73 09-Mar-79 04-May-79 24-Oct-79 5 FUKUSHIMA-DAINI-1 BWR 1067 TEPCO Operating TOSHIBA 16-Mar-76 17-Jun-81 31-Jul-81 20-Apr-82 5 FUKUSHIMA-DAINI-2 BWR 1067 TEPCO Operating HITACHI 25-May-79 26-Apr-83 23-Jun-83 03-Feb-84 5 FUKUSHIMA-DAINI-3 BWR 1067 TEPCO Operating TOSHIBA 23-Mar-81 18-Oct-84 14-Dec-84 21-Jun-85 5 FUKUSHIMA-DAINI-4 BWR 1067 TEPCO Operating HITACHI 28-May-81 24-Oct-86 17-Dec-86 25-Aug-87 6 TOKAI-1 GCR 159 JAPCO Decommissioned GEC 01-Mar-61 04-May-65 10-Nov-65 25-Jul-66 31-Mar-98 7 TOKAI-2 BWR 1056 JAPCO Operating GE 03-Oct-73 18-Jan-78 13-Mar-78 28-Nov-78 8 HAMAOKA-1 BWR 515 CHUBU Operating TOSHIBA 10-Jun-71 20-Jun-74 13-Aug-74 17-Mar-76 8 HAMAOKA-2 BWR 806 CHUBU Operating TOSHIBA 14-Jun-74 28-Mar-78 04-May-78 29-Nov-78 8 HAMAOKA-3 BWR 1056 CHUBU Operating TOSHIBA 18-Apr-83 21-Nov-86 20-Jan-87 28-Aug-87 8 HAMAOKA-4 BWR 1092 CHUBU Operating TOSHIBA 13-Oct-89 02-Dec-92 27-Jan-93 03-Sep-93 8
HAMAOKA-5
ABWR
1325
CHUBU
Under Construction
TOSHIBA
19-March-99
01-Aug-05
|
9 IKATA-1 PWR 538 SHIKOKU Operating MHI 15-Jun-73 29-Jan-77 17-Feb-77 30-Sep-77 9 IKATA-2 PWR 538 SHIKOKU Operating MHI 21-Feb-78 31-Jul-81 19-Aug-81 19-Mar-82 9 IKATA-3 PWR 846 SHIKOKU Operating MHI 01-Nov-86 23-Feb-94 29-Mar-94 15-Dec-94 10 SENDAI-1 PWR 846 KYUSHU Operating MHI 15-Dec-79 25-Aug-83 16-Sep-83 04-Jul-84 10 SENDAI-2 PWR 846 KYUSHU Operating MHI 12-Oct-81 18-Mar-85 05-Apr-85 28-Nov-85 11 GENKAI-1 PWR 529 KYUSHU Operating MHI 15-Sep-71 28-Jan-75 14-Feb-75 15-Oct-75 11 GENKAI-2 PWR 529 KYUSHU Operating MHI 01-Feb-77 21-May-80 03-Jun-80 30-Mar-81 11 GENKAI-3 PWR 1127 KYUSHU Operating MHI 01-Jun-88 28-May-93 15-Jun-93 18-Mar-94 11 GENKAI-4 PWR 1127 KYUSHU Operating MHI 15-Jul-92 23-Oct-96 12-Nov-96 25-Jul-97 12
KAMINOSEKI-1
ABWR
1373(Gross)
CHUGOKU
Planned
2007
2012
12
KAMINOSEKI-2
ABWR
1373(Gross)
CHUGOKU
Planned
2010
2015
13 SHIMANE-1 BWR 439 CHUGOKU Operating HITACHI 02-Jul-70 01-Jun-73 02-Dec-73 29-Mar-74 13 SHIMANE-2 BWR 789 CHUGOKU Operating HITACHI 02-Feb-85 25-May-88 11-Jul-88 10-Feb-89 13
SIMANE-3
ABWR
1373(Gross)
CHUGOKU
Planned
2004
2010
14 TAKAHAMA-1 PWR 780 KEPCO Operating WH 25-Apr-70 14-Mar-74 27-Mar-74 14-Nov-74 14 TAKAHAMA-2 PWR 780 KEPCO Operating MHI 09-Mar-71 20-Dec-74 17-Jan-75 14-Nov-75 14 TAKAHAMA-3 PWR 830 KEPCO Operating MHI 12-Dec-80 17-Apr-84 09-May-84 17-Jan-85 14 TAKAHAMA-4 PWR 830 KEPCO Operating MHI 19-Mar-81 11-Oct-84 01-Nov-84 05-Jun-85 15 OHI-1 PWR 1120 KEPCO Operating WH 26-Oct-72 02-Dec-77 23-Dec-77 27-Mar-79 15 OHI-2 PWR 1120 KEPCO Operating WH 08-Dec-72 14-Sep-78 11-Oct-78 05-Dec-79 15 OHI-3 PWR 1127 KEPCO Operating MHI 03-Oct-87 17-May-91 07-Jun-91 18-Dec-91 15 OHI-4 PWR 1127 KEPCO Operating MHI 13-Jun-88 28-May-92 19-Jun-92 02-Feb-93 16 MIHAMA-1 PWR 320 KEPCO Operating WH 01-Feb-67 29-Jul-70 08-Aug-70 28-Nov-70 |
16 MIHAMA-2 PWR 470 KEPCO Operating WH/MHI 29-May-68 10-Apr-72 21-Apr-72 25-Jul-72 16 MIHAMA-3 PWR 780 KEPCO Operating MHI 07-Aug-72 28-Jan-76 19-Feb-76 01-Dec-76 17 TSURUGA-1 BWR 341 JAPCO Operating GE 24-Nov-66 03-Oct-69 16-Nov-69 14-Mar-70 17 TSURUGA-2 PWR 1115 JAPCO Operating MHI 06-Nov-82 28-May-86 19-Jun-86 17-Feb-87 17
TSURUGA-3
APWR
1538(Gross)
JAPCO
Planned
2006
2011
17
TSURUGA-4
APWR
1538(Gross)
JAPCO
Planned
2006
2011
18 SHIKA-1 BWR 505 HOKURIKU Operating HITACHI 01-Jul-89 20-Nov-92 12-Jan-93 30-Jul-93 18
SHIKA-2
ABWR
1358(Gross)
HOKURIKU
Under Construction
HITACHI
27-Aug-99
01-Mar-06
19 KASHIWAZAKI KARIWA-1 BWR 1067 TEPCO Operating TOSHIBA 05-Jun-80 12-Dec-84 13-Feb-85 18-Sep-85 19 KASHIWAZAKIKARIWA-2 BR 1067 TEPCO Operating TOSHIBA 18-Nov-85 30-Nov-89 08-Feb-90 28-Sep-90 19 KASHIWAZAKI KARIWA-3 BWR 1067 TEPCO Operating TOSHIBA 20-Jun-85 19-Oct-92 08-Dec-92 11-Aug-93 19 KASHIWAZAKI KARIWA-4 BWR 1067 TEPCO Operating HITACHI 07-Mar-89 01-Nov-93 21-Dec-93 11-Aug-94 19 KASHIWAZAKI KARIWA-5 BWR 1067 TEPCO Operating HITACHI 05-Mar-90 20-Jul-89 12-Sep-89 10-Apr-90 19 KASHIWAZAKI KARIWA-6 ABWR 1315 TEPCO Operating TOSHIBA/GE 03-Nov-92 18-Dec-95 29-Jan-96 07-Dec-96 19 KASHIWAZAKI KARIWA-7 ABWR 1315 TEPCO Operating HITACHI/GE 01-Jul-93 01-Nov-96 17-Dec-96 02-Jul-97
20
MAKI
BWR
796
TOHOKU
Planned
2006
2012
21
HIGASHI DORI 1
BWR
1067
TOHOKU
Under Construction
TOSHIBA
24-Dec-98
Jul-05
(not on map) JPDR-II BWR 13 JAERI Decommissioned GE 01-Dec-60 22-Aug-63 26-Oct-63 26-Oct-63 06-Dec-82 (not on map) MONJU FBR 246 JNC Under Construction MHI 10-May-86 05-Apr-94 29-Aug-94 |
1
OMA
ABWR
1383(Gross)
Electric Power Development
Planned
Mar-05
Jul-10
2 TOMARI-1 PWR 550 HEPCO Operating MHI 02-Jul-85 16-Nov-88 06-Dec-88 22-Jun-89
2
TOMARI-3
PWR
866
HEPCO
Planned
2003
2009
2 TOMARI-2 PWR 550 HEPCO Operating MHI 05-Aug-86 25-Jul-90 27-Aug-90 12-Apr-91
3 ONAGAWA-1 BWR 498 TOHOKU Operating TOSHIBA 08-Jul-80 18-Oct-83 18-Nov-83 01-Jun-84
3 ONAGAWA-2 BWR 796 TOHOKU Operating TOSHIBA 12-Apr-91 02-Nov-94 23-Dec-94 28-Jul-95
3 ONAGAWA 3 BWR 796 TOHOKU Operating TOSHIBA 23-Jan-98 26-Apr-01 30-May-01 30-Jan-02
4 FUKUSHIMA-DAIICHI-1 4 BWR 439 TEPCO Operating GE 25-Jun-67 10-Oct-70 17-Nov-70 26-Mar-71
4 FUKUSHIMA-DAIICHI-2 BWR 760 TEPCO Operating GE/TOSHIBA 09-Jun-69 10-May-73 24-Dec-73 18-Jul-74
4 FUKUSHIMA-DAIICHI-3 BWR 760 TEPCO Operating TOSHIBA 28-Dec-70 06-Sep-74 26-Oct-74 27-Mar-76
4 FUKUSHIMA-DAIICHI-4 BWR 760 TEPCO Operating HITACHI 12-Feb-73 28-Jan-78 24-Feb-78 12-Oct-78
4 FUKUSHIMA-DAIICHI-5 BWR 760 TEPCO Operating TOSHIBA 22-May-72 26-Aug-77 22-Sep-77 18-Apr-78
4 FUKUSHIMA-DAIICHI-6 BWR 1067 TEPCO Operating GE/TOSHIBA 26-Oct-73 09-Mar-79 04-May-79 24-Oct-79
5 FUKUSHIMA-DAINI-1 BWR 1067 TEPCO Operating TOSHIBA 16-Mar-76 17-Jun-81 31-Jul-81 20-Apr-82
5 FUKUSHIMA-DAINI-2 BWR 1067 TEPCO Operating HITACHI 25-May-79 26-Apr-83 23-Jun-83 03-Feb-84
5 FUKUSHIMA-DAINI-3 BWR 1067 TEPCO Operating TOSHIBA 23-Mar-81 18-Oct-84 14-Dec-84 21-Jun-85
5 FUKUSHIMA-DAINI-4 BWR 1067 TEPCO Operating HITACHI 28-May-81 24-Oct-86 17-Dec-86 25-Aug-87
6 TOKAI-1 GCR 159 JAPCO Decommissioned GEC 01-Mar-61 04-May-65 10-Nov-65 25-Jul-66 31-Mar-98
7 TOKAI-2 BWR 1056 JAPCO Operating GE 03-Oct-73 18-Jan-78 13-Mar-78 28-Nov-78
8 HAMAOKA-1 BWR 515 CHUBU Operating TOSHIBA 10-Jun-71 20-Jun-74 13-Aug-74 17-Mar-76
8 HAMAOKA-2 BWR 806 CHUBU Operating TOSHIBA 14-Jun-74 28-Mar-78 04-May-78 29-Nov-78
8 HAMAOKA-3 BWR 1056 CHUBU Operating TOSHIBA 18-Apr-83 21-Nov-86 20-Jan-87 28-Aug-87
8 HAMAOKA-4 BWR 1092 CHUBU Operating TOSHIBA 13-Oct-89 02-Dec-92 27-Jan-93 03-Sep-93
8
HAMAOKA-5
ABWR
1325
CHUBU
Under Construction
TOSHIBA
19-March-99
01-Aug-05
9 IKATA-1 PWR 538 SHIKOKU Operating MHI 15-Jun-73 29-Jan-77 17-Feb-77 30-Sep-77
9 IKATA-2 PWR 538 SHIKOKU Operating MHI 21-Feb-78 31-Jul-81 19-Aug-81 19-Mar-82
9 IKATA-3 PWR 846 SHIKOKU Operating MHI 01-Nov-86 23-Feb-94 29-Mar-94 15-Dec-94
10 SENDAI-1 PWR 846 KYUSHU Operating MHI 15-Dec-79 25-Aug-83 16-Sep-83 04-Jul-84
10 SENDAI-2 PWR 846 KYUSHU Operating MHI 12-Oct-81 18-Mar-85 05-Apr-85 28-Nov-85
11 GENKAI-1 PWR 529 KYUSHU Operating MHI 15-Sep-71 28-Jan-75 14-Feb-75 15-Oct-75
11 GENKAI-2 PWR 529 KYUSHU Operating MHI 01-Feb-77 21-May-80 03-Jun-80 30-Mar-81
11 GENKAI-3 PWR 1127 KYUSHU Operating MHI 01-Jun-88 28-May-93 15-Jun-93 18-Mar-94
11 GENKAI-4 PWR 1127 KYUSHU Operating MHI 15-Jul-92 23-Oct-96 12-Nov-96 25-Jul-97
12
KAMINOSEKI-1
ABWR
1373(Gross)
CHUGOKU
Planned
2007
2012
12
KAMINOSEKI-2
ABWR
1373(Gross)
CHUGOKU
Planned
2010
2015
13 SHIMANE-1 BWR 439 CHUGOKU Operating HITACHI 02-Jul-70 01-Jun-73 02-Dec-73 29-Mar-74
13 SHIMANE-2 BWR 789 CHUGOKU Operating HITACHI 02-Feb-85 25-May-88 11-Jul-88 10-Feb-89
13
SIMANE-3
ABWR
1373(Gross)
CHUGOKU
Planned
2004
2010
14 TAKAHAMA-1 PWR 780 KEPCO Operating WH 25-Apr-70 14-Mar-74 27-Mar-74 14-Nov-74
14 TAKAHAMA-2 PWR 780 KEPCO Operating MHI 09-Mar-71 20-Dec-74 17-Jan-75 14-Nov-75
14 TAKAHAMA-3 PWR 830 KEPCO Operating MHI 12-Dec-80 17-Apr-84 09-May-84 17-Jan-85
14 TAKAHAMA-4 PWR 830 KEPCO Operating MHI 19-Mar-81 11-Oct-84 01-Nov-84 05-Jun-85
15 OHI-1 PWR 1120 KEPCO Operating WH 26-Oct-72 02-Dec-77 23-Dec-77 27-Mar-79
15 OHI-2 PWR 1120 KEPCO Operating WH 08-Dec-72 14-Sep-78 11-Oct-78 05-Dec-79
15 OHI-3 PWR 1127 KEPCO Operating MHI 03-Oct-87 17-May-91 07-Jun-91 18-Dec-91
15 OHI-4 PWR 1127 KEPCO Operating MHI 13-Jun-88 28-May-92 19-Jun-92 02-Feb-93
16 MIHAMA-1 PWR 320 KEPCO Operating WH 01-Feb-67 29-Jul-70 08-Aug-70 28-Nov-70
16 MIHAMA-2 PWR 470 KEPCO Operating WH/MHI 29-May-68 10-Apr-72 21-Apr-72 25-Jul-72
16 MIHAMA-3 PWR 780 KEPCO Operating MHI 07-Aug-72 28-Jan-76 19-Feb-76 01-Dec-76
17 TSURUGA-1 BWR 341 JAPCO Operating GE 24-Nov-66 03-Oct-69 16-Nov-69 14-Mar-70
17 TSURUGA-2 PWR 1115 JAPCO Operating MHI 06-Nov-82 28-May-86 19-Jun-86 17-Feb-87
17
TSURUGA-3
APWR
1538(Gross)
JAPCO
Planned
2006
2011
17
TSURUGA-4
APWR
1538(Gross)
JAPCO
Planned
2006
2011
18 SHIKA-1 BWR 505 HOKURIKU Operating HITACHI 01-Jul-89 20-Nov-92 12-Jan-93 30-Jul-93
18
SHIKA-2
ABWR
1358(Gross)
HOKURIKU
Under Construction
HITACHI
27-Aug-99
01-Mar-06
19 KASHIWAZAKI KARIWA-1 BWR 1067 TEPCO Operating TOSHIBA 05-Jun-80 12-Dec-84 13-Feb-85 18-Sep-85
19 KASHIWAZAKIKARIWA-2 BR 1067 TEPCO Operating TOSHIBA 18-Nov-85 30-Nov-89 08-Feb-90 28-Sep-90
19 KASHIWAZAKI KARIWA-3 BWR 1067 TEPCO Operating TOSHIBA 20-Jun-85 19-Oct-92 08-Dec-92 11-Aug-93
19 KASHIWAZAKI KARIWA-4 BWR 1067 TEPCO Operating HITACHI 07-Mar-89 01-Nov-93 21-Dec-93 11-Aug-94
19 KASHIWAZAKI KARIWA-5 BWR 1067 TEPCO Operating HITACHI 05-Mar-90 20-Jul-89 12-Sep-89 10-Apr-90
19 KASHIWAZAKI KARIWA-6 ABWR 1315 TEPCO Operating TOSHIBA/GE 03-Nov-92 18-Dec-95 29-Jan-96 07-Dec-96
19 KASHIWAZAKI KARIWA-7 ABWR 1315 TEPCO Operating HITACHI/GE 01-Jul-93 01-Nov-96 17-Dec-96 02-Jul-97
20
MAKI
BWR
796
TOHOKU
Planned
2006
2012
21
HIGASHI DORI 1
BWR
1067
TOHOKU
Under Construction
TOSHIBA
24-Dec-98
Jul-05
(not on map) JPDR-II BWR 13 JAERI Decommissioned GE 01-Dec-60 22-Aug-63 26-Oct-63 26-Oct-63 06-Dec-82
(not on map) MONJU FBR 246 JNC Under Construction MHI 10-May-86 05-Apr-94 29-Aug-94
Source: Informed Data from Japan to IAEA Power Reactor Information System as of 31-Jan-2003; nuclear power plants In The World 2002, Japan Atomic Industrial Forum; Outlook of Electric Supply Plan (March 2003), METI.